CIDT will deliver Plugins and URI Resolver for Polywrap Go Client
Backlog
Proposed User Stories estimated with Story Points (SP)
Epic | User Story | SP Estimate |
---|---|---|
Plugins | Plugin Wrapper | 5 |
Plugins | Plugin Module | 3 |
Plugins | Plugin Codegen | 3 |
Plugins | Plugin Example: FS Plugin | 1 |
URI Resolver | Extendable URI Resolver | 3 |
URI Resolver | URI Resolver Wrapper | 3 |
URI Resolver | URI Resolver Aggregator Base | 2 |
Misc | Codegen for Go types | 5 |
Total | 25 |
SP Team Roles & SP Cost
Proposed Dev Team specialties, along with estimated individual time commitment and cost per Story Point (SP)
Team Roles | Time Commitment (Hrs/SP) | Rate ($/Hr) | Cost/SP |
---|---|---|---|
Project Manager, Scrum Master | 1 | $120 | $120.00 |
Tech Lead, Lead Architect | 2 | $150 | $300.00 |
Sr. Golang Developer | 8 | $120 | $960.00 |
Total Team 1SP Cost | $1,380.00 | ||
Total Story Points | 25 | ||
Total Cost | $34,500.00 |
Velocity & Estimated Timeline
Polywrap DAO uses Story Points (SP) to derive duration estimates for development projects. We define Baseline SP = as approximately 1 Day of Individual/Team effort.
Target Monthly Velocity | Estimated Start | Estimated Duration |
---|---|---|
20 SP/Month | 23-Jan-23 | ~1-1.5 Months |
Sponsor Review
Sponsor:
- Jordan
- Nester
Terms
By submtting this proposal, I understand that the DAO and my sponsor will be evaluating whether my work meets the acceptance criteria. If it does not, the DAO will determine what percentage of the proposal cost to pay, if any.
I also understand that I may not begin work until it is confirmed that the Snapshot proposal has passed.
[ X ] I agree